# Release process Two-week cycles. The version is cut on a Tuesday, spends two days on staging with the replay suite running against it, and goes to production on Thursday morning behind a flag that is opened to 5 %, then 50 %, then everyone, over the following day. A fix that must not wait for the cycle goes out as a patch release, which skips staging only if the change is a single-line configuration value. Anything larger waits for the next morning window. Rollback is a flag flip and takes under a minute, which is why every release must be able to run against the previous schema. That constraint is the reason migrations are split into an additive change now and a destructive change two releases later.