Release process¶
Two-week cycles. The version is cut on a Tuesday, spends two days on staging with the replay suite
running against it, and goes to production on Thursday morning behind a flag that is opened to 5 %,
then 50 %, then everyone, over the following day.
A fix that must not wait for the cycle goes out as a patch release, which skips staging only if the
change is a single-line configuration value. Anything larger waits for the next morning window.
Rollback is a flag flip and takes under a minute, which is why every release must be able to run
against the previous schema. That constraint is the reason migrations are split into an additive
change now and a destructive change two releases later.